Thursday, November 29, 2012

Range tee project

Earlier this fall, we tore out the fence between the range tee and the chipping practice area.  Throughout the fall we have been adding soil to the once practice bunker on top of the range tee.  Today we finished adding soil to this area.  We will let this settle out through the winter, regrade it next spring and then seed it into the same grass on the range tee.  This area will be an extension of the range tee and will be most widely used as another hitting location during outings.





Wednesday, November 28, 2012

Irrigation pumps

Last Monday, we had our irrigation pumps pulled up and sent to Toledo to get one of them rebuilt and the other pump replaced.  The pumps were installed in 2001, one of the pumps was replaced in 2006, the other pump has yet to be rebuilt or replaced.  We were starting to see the effects of the older pump wearing down.  We should be able to pump 1200 GPM, we were only able to pump 900 GPM.  This wear on the pumps is caused by the silt and sand that comes through the pumps.  The rebuilt/replaced pumps will have a dirty water kit on them to help combat excessive wear.

First step was to take the 60hp motors off.

The motors will be stored up on the service path for the winter.

We had a local company do the crane work.  We needed all the length they could get.  This spot on the lawn is the only access point to the pumps via crane.

The motors are 600lbs a piece and the pumps are 1000lbs.  Not that heavy, but still quite a load for the reach that was required.

Pulling the first pump.


They were laid on a trailer to be sent to Toledo.

Pulling the second pump.

The pumps go down twelve feet into a wet well along the river. 

You can see which pump was replaced in 2006, this pump will be rebuilt.  The older pump will be replaced.

Monday, November 19, 2012

Busy morning

What we accomplished today:

Mowing fairways


Hanging Christmas lights


Pulling the irrigation pumps




More on this later....

Range tee landscape bed

Last week we tore out the steps and landscape bed that was between the two driving range tees.  We will sod this area next spring.  It was removed because: 1. It wasn't used  2. It was unsightly.





This will settle over the winter.  Next spring we will level it off with more soil and then sod it.

Thursday, November 15, 2012

Frost projects

This morning we had heavy frost again.  Here is what we were able to accomplish:

The hedge row between the range tee and the chipping area needed to be trimmed.


We cut a good 8 feet off the hedge.

After all the debris was cleaned up, it looks great.

Then there is our staple frost job - splitting wood.  We delivered three loads of wood to members yesterday.

Wednesday, November 14, 2012

Rain day project

This past Monday was another rainy, cold and windy day.  We got .6" here at the course.  As stated in an earlier post, we are now into winter projects and when we can't be outside - we get things done inside. 

Our maintenance building has a room for chemical storage.  It also houses other items such as hoses, paint, rope and stake along with all our course supplies such as flags, flagsticks and tee markers.  This room needs to be kept at or above 40 degrees.  Many of the chemicals that we store can not freeze or they will lose their effectiveness.  We do have a very efficient heater in that room which does a great job at warming up the room, there was only one problem - it never stopped running.  While the walls are insulated around this room, the ceiling was not.  In fact there was not a ceiling, it was wide open up to the metal roof.  All of our heat was escaping very easily out of the building.  The past two days we put up plywood for a ceiling in this chemical room along with insulation on top of the plywood.  I went in the room this morning, usually I would find a drafty room with a the heater running.  Today I found a warm cozy room with no drafts and THE HEATER WASN'T RUNNING!

There was no ceiling, only a metal roof.  Very inefficient.

First thing we had to do was get rid of the junk stored in the rafters.


We then put up plywood and insulation.


We had to rent a lift to get the job done safely and quickly.


Finished job.  I can tell a big difference.

These types of projects are not budgeted.  Throughout the year we have been able to save money and stay under budget.  If I continue to stay under budget over the course of a season I like to tackle projects such as this.  These types of projects might not show immediate returns to the members but in the long run will only benefit the operation.  The cost of this project was relatively low compared to the savings we will see in energy costs.

Monday, November 12, 2012

Parts room

We are getting into the time of year that we are routinely getting days where we cannot perform any maintenance out on the course due to rain, wind and cold temps.  During these days all the part time seasonal help is sent home and it gives the full time employees an opportunity to start working on our typical winter projects.  Over the past few weeks on rainy days we have been spending some time on our parts room.  This little room needed a complete makeover.  We had parts to machines we haven't owned in some time and the shear volume of parts made finding what you were looking for cumbersome and inefficient.  We now have a parts room where we only have on inventory the necessary parts, they are labeled, clean and organized.
First we had to take all the parts out of the room.

It's amazing how much stuff can fit into a 8 X 10 room.

We then put up plywood on all the walls.  It was just open insulation.

Next was a nice looking coat of paint.

We spent a lot of time going through all the parts, categorizing them and throwing away the junk.

We now have a clean, organized parts room.  We can find items efficiently and we no longer have parts on inventory that we don't need.  A clean shop is a happy shop.

Tree removal

Friday morning we removed 3 dead trees from the course.  A Maple behind 11 tee, an Ash along 11 fairway and a Buckeye along 8 tee.  These three trees were quite large and in hard to reach places, therefore we had a tree care company come in and help us with the removal.  We chose to get them done on Friday because of the rain that was forecast to hit Findlay.  The ground conditions were dry and firm enough for the large equipment that we would need to do the job.  If we were not able to get them done on Friday we would have had to wait until the ground froze, and last year that did not happen.

Tuesday, November 6, 2012

Irrigation blow-out

Yesterday was the unofficial end of the season - we blew out the irrigation system.
This process takes two 375cfm compressors and about 9 hours to complete.  Today we will be blowing out the fresh water - 1st tee, 15th hole, pool and tennis areas.

Thursday, November 1, 2012

Tree planting

Three trees were planted today.  We planted a Scarlet Oak between 2/17, an London Plane between 1/2 and a Blue Spruce between 4/dump area.  We purchased the three trees two weeks ago.  Our Horticulturist Tim Stumpp and I went to our nursery supplier and hand picked the trees that we wanted for the spot that we wanted to put it in.  The trees were delivered yesterday.

The root balls on these trees were 4' X 4' X 3' deep


There are a few other London Plane trees near this one.  When we plant trees at FCC we are thinking long term (50 year plan).  This tree is going to be a great compliment to the course in 50 years.  This tree will potentially grow to over 100' tall.

This Scarlet Oak will provide exceptional fall color.  It produces a vibrant bright red leaf.  When we picked this tree out, it was in full fall color and very beautiful. 
This tree was donated by a member.  Member donations only work if there is a need for a tree and the tree cultivar along with the planting location is determined by the Superintendent.


This Blue Spruce will help fill in a gap between 4 fairway and our dump area.